KUALA LUMPUR, Nov 24 (Bernama) -- BMI expects El Nino to put existing data centres to an early stress test as capacity continues to expand rapidly in markets facing water supply constraints.
BMI, a unit of Fitch Solutions, said in locations where El Nino raises drought risk, it expects the 2026/27 event to amplify these concerns: shortages, rationing and emergency measures make data centre water use far more visible.
“That makes El Nino an early stress test for existing data centres, whose water supply arrangements and cooling systems will be tested in a dry 2027, and a downside risk for planned ones, through the risk of tighter permitting conditions, approval delays and costlier water-saving cooling,” it said in a statement released today.
Of the 83.6GW of data centre capacity in BMI’s data centre projects database, around 21 per cent sits in locations where El Nino raises water stress.
To identify these locations, BMI has classified each project location as rain-fed or snow-fed, based on how much of the water in its supply basin comes from snowmelt, tested rain-fed locations against a global drought index for 2013-2026 and snow-fed locations against snowmelt and river runoff in their supply basins since 1951, comparing El Nino periods with neutral ones, and then checked news, utility and government reports for documented water shortages in past El Nino years.
The exposed capacity includes around 3.8GW of live capacity, which faces the stress test, and around 13.8GW in the pipeline, which faces the downside risk.
For 14.9GW, at 16 locations, past El Nino years brought documented water shortages, rationing or emergency measures, and 11.6GW of it is still under construction or planned.
“Asia-Pacific accounts for 92 per cent of highly exposed capacity, and because much of the exposed capacity is not yet built, permitting conditions and cooling choices can still adapt,” it said.
BMI said the Johor-Singapore-Batam cluster is the most exposed, combining 6.6GW of capacity, 4.7GW of it still in the pipeline, with rainfall that becomes far less reliable during El Nino.
It noted that drought occurred in 25-37 per cent of El Nino-period months there since 2013, against zero to three per cent of neutral months, and in the 2015/16 El Nino the Linggiu reservoir on the Johor River, which supplies both Johor and Singapore, fell to record lows.
“The 2023/24 event was wet locally, so El Nino raises the odds of a dry year sharply rather than guaranteeing one.
“Policy is already moving: Johor has tightened approvals for water-intensive data centres since 2025, and Malaysia's federal government said in October 2026 that states without sufficient water will not host data centres,” it added.